Pitt Greene EMC Arba POD 115kV Substation
Client: Duke Energy
Location: Snow Hill, NC
Completion: March 13, 2020 – April 27, 2020
Scope/Description:
- End of life replacement of the coupling capacitor on the Arba 115kVTap Line
- Replaced CC at the Arba 115kV Tap Line
- Installed new 115kV CCVT on new standard structure
- Relocated existing line trap to new structure
- Installed new line tuner & CCVT junction box
- Removed existing CCVT /LT structure & foundation
- Installed (1) new augered pier foundation
- Installed new 2” PVC conduit
- FB Timberline
Highlight:
This project was completed as part FB Timberline’s MSA with Duke Energy.