Pitt Greene EMC Arba POD 115kV Substation

Client: Duke Energy

Location: Snow Hill, NC

Completion: March 13, 2020 – April 27, 2020

Scope/Description:

  • End of life replacement of the coupling capacitor on the Arba 115kVTap Line
  • Replaced CC at the Arba 115kV Tap Line
  • Installed new 115kV CCVT on new standard structure
  • Relocated existing line trap to new structure
  • Installed new line tuner & CCVT junction box
  • Removed existing CCVT /LT structure & foundation
  • Installed (1) new augered pier foundation
  • Installed new 2” PVC conduit

Highlight: This project was completed as part FB Timberline’s MSA with Duke Energy.

 