Selma 230kV Substation

Client: Duke Energy

Location: Selma, NC

Completion: march 2020 – April 2020

Scope/Description:

  • End of life replacement of CCVT on West 230kV Bus and coupling capacitor / wave trap on the 115kV Lee Plant line
  • Replace CCVT and install new 795 ACSR jumper at West 230kV Bus
  • Install new 115kV CCVT including foundation and line trap on new structure
  • Install new line tuner and CCVT junction box
  • Install new 1000MCM CU jumpers to new equipment

Highlight: This project was completed as part FB Timberline’s MSA with Duke Energy.