Sarpy Transmission Project
Client: Omaha Public Power District
Location: Papillion, NE
Length: 10 miles
Completion Date: December 2019
Scope/Description:
- Removal of 10 miles of 3-phase 69kV line.
- Install new 7 miles, twin-bundle 345kV line and a single 161kV line
- Installation of 126 concrete foundations, and erection of 111 monopole structures
- FB Timberline