Electric Vehicle Charging Stations
					Client: SAI Group
Location: 9 sites in Nevada, Utah, New Mexico and Arizona
Completion: November 2018 to Feb 2019
Scope/Description:
- Install 4 to 6 new dispensers at each site location
 
- Provide electrical work, excavations and underground utility work, paving, landscaping, and site restoration
 
- Extensive planning and coordination with local utilities
 
- Material procurement for conductors, lugs/termination materials, trench and direct bore PVC, key cabinet, 120V GFCI receptacle, ground rods, and edging material
 
- FB Utility Construction
 
Highlight:
FBUC worked with the client to relocate vault location due to landowner request.