Electric Vehicle Charging Stations

Client: SAI Group

Location: 9 sites in Nevada, Utah, New Mexico and Arizona

Completion: November 2018 to Feb 2019

Scope/Description:

  • Install 4 to 6 new dispensers at each site location
  • Provide electrical work, excavations and underground utility work, paving, landscaping, and site restoration
  • Extensive planning and coordination with local utilities
  • Material procurement for conductors, lugs/termination materials, trench and direct bore PVC, key cabinet, 120V GFCI receptacle, ground rods, and edging material
  • FB Utility Construction

Highlight:

FBUC worked with the client to relocate vault location due to landowner request.

NEXT

Through an establishment of trust and earning a reputation for excellence, we can develop rewarding, long-term relationships.

Forbes Bros. Group of Companies has over 40 years’ experience constructing power lines across North America. With over 2500 pieces of owned construction equipment, our capabilities are limitless. With over 2500 pieces of owned construction equipment, our capabilities are limitless. With over 2500 pieces of owned construction equipment, our capabilities are limitless.