Redwater South Rail Yard Expansion – 25 kV

Client: Pembina Pipeline Corporation

Length: 3.2 km

Location: Redwater, AB

Timeline: June 2018 to December 2018

Scope/Description:

  • Design, procurement, and construction of 25kV overhead power distribtuon and lighting systems throughout the rail yard facility
  • Installation of 288 single wood poles, overhead conductor, fiber, davit arms and luminaires
  • #2 ACSR primary
  • Direct embedment foundations

Highlight: Project work site had extreme space constraints due to several live railway tracks and other contractors working on site.