Bruenning’s Breeze Wind Farm

Client: IEA Renewables

Location: Raymondville, TX

Length: 281,000 linear ft

Completion: June 2017 – October 2017

Scope/Description:

  • Procure and install 281,000’ of 35kV underground cable
  • Tri-bundle configuration with 12F single mode fiber optic cable and 7#7 Copperweld collection system ground
  • 10 circuits installed with 5,000’ of 8” and 10” boring for 35kV cables
  • Install and test 76, 3500kVA pad mount transformers
  • Terminations at transformers along with 35kV direct bury splicing

Highlight:

Crews performed over 700 35kV and 15kV termination to complete this project.