138kV Transmission Lines

Client: City of Medicine Hat

Length: 20 km

Completion Date: December 2017

Scope/Description:

  • Single pole, H-frame, or 3-pole structures: 10L – 86 structures, 20L – 224 structures
  • 795 ACSR, #2 underbuild, OPGW
  • Direct embedment, culverts
  • Project scope involved uprating the existing line from 69kV to 138kV for both circuits (MH-10L and MH-20L)

Highlight:

Forbes Bros. procured all line materials for the project and provided material management services.