Bipole III – 500kV

Client: Manitoba Hydro

Length: 700 km

Timeline: October 2015 – April 2018

Location: Manitoba, Canada

Scope/Description:

  • 1400 structures – steel lattice towers, guyed and self-supporting
  • Helicopter and conventional crane erection
  • 4-bundle, 1590 Falcon ACSR with OPGW and OHSW
  • Helical piles, cast-in-place concrete piles, micropiles, rock set and concrete mat foundations
  • Right-of-way brushing and clearing
  • Access road construction over 550 km
  • Owner driven landowner mitigations required access matting at over 300 sites
  • Establishment of remote camp accommodations
  • First Nations engagement and landowner involvement for flow through benefits to local communities

Highlight: A portion of line was constructed through the Tom Lamb Wildlife Management Area – a major breeding and staging area for waterfowl and habitat for moose, wolves, and black bears.

bipole

This path took 40 years.

bipole Our Mission, Vision and Values guide and align us to being the contract of choice in all markets we enter. bipole The Forbes Bros. Group of Companies shows up ready to deliver with 40 years of experience behind us. bipole With over 2500 pieces of owned construction equipment, our capabilities are limitless. bipole The Forbes Bros. Group of Companies is now one of the largest private, family-owned businesses in our market. bipole Safety is our priority, always. Every day we work to show up better than we did the day before.