Columbia Valley Transmission Line – 230kV & 69kV

Length: 115 km

Completion: October 2012 (energized)

Location: golden, BC

Scope/Description:

  • 491 wood pole H-frames and 19 steel poles
  • Single circuit 1034 Bluebird ACSR
  • Helicopter and conventional crane erection
  • Limited access – mountainous terrain

Highlight: Full EPC services provided by Forbes Bros for the 69kV portion of line and procure / construct for the 230kV portion.

We understand the difference between talking the talk and walking the walk. We know that to achieve success we have to live it and live up to it – every single day. Our Mission, Vision and Values guide and align us to being the contract of choice in all markets we enter. The Forbes Bros. Group of Companies shows up ready to deliver with 40 years of experience behind us. The Forbes Bros. Group of Companies is now one of the largest private, family-owned businesses in our market. NEXT