Sarpy Transmission Project

Client: Omaha Public Power District

Location: Papillion, NE

Length: 10 miles

Completion: April 2019 – December 2019

Scope/Description:

  • Removal of 10 miles of 3-phase 69kV line.
  • Install new 7 miles, twin-bundle 345kV line and a single 161kV line
  • Installation of 126 concrete foundations, and erection of 111 monopole structures