Voltage Drop Rectification

Client: BC Hydro & Power Authority

Location: Pitt Meadows, BC

Completion Date: September 6, 2018

Scope/Description:

  • Customer losing over 10 – 25V when under load.
  • Outage coordination for changeover
  • Parallel runs of cable

Highlight(s):

  • Installed triple run of 266 Triplex with new transformer for dedicated service.

Trusted experts building powerful solutions.

Our Mission, Vision and Values guide and align us to being the contract of choice in all markets we enter. With over 2500 pieces of owned construction equipment, our capabilities are limitless. The Forbes Bros. Group of Companies shows up ready to deliver with 40 years of experience behind us.